Wheeling Park District Community

Arctic Splash

Cost of Construction:  $3,515,286

Size:  20,778 SF

Status: December 1999

Challenge/Goal:  The Park District wanted to add an indoor aquatic center to the facility to provide additional programming opportunities. The fitness center also needed to be expanded to accommodate its increasing membership.

Solution:  SRBL spent a great deal of time with the District’s Board members, listening to their thoughts and needs, and incorporated what was heard into the design. The indoor aquatic center features two pools: a zero-depth edge leisure pool with a vortex and water play features and a four-lane lap pool. The expanded fitness center accommodated the community’s growing interest in fitness.

SRBL Client List
  • Bartlett Park District
  • Carmel High School
  • Foglia YMCA
  • Gurnee Park District
  • Kankakee Valley Park District
  • Lake Forest Hospital Health & Fitness Institute
  • Norridge Park District
  • Roselle Park District
  • Schaumburg Park District
  • Streator Family YMCA
  • Twinbrook Family YMCA (now Campanelli YMCA)
  • Wauconda Park District
  • Wheeling Park District
  • Bethesda-Chevy Chase Branch of Metropolitan YMCA
  • Elk Grove Park District
  • Grayslake Community Park District
  • Hanover Park Park District
  • Kettle-Moraine YMCA
  • Lombard Park District
  • Palatine Park District
  • Round Lake Area Park District
  • Streamwood Park District
  • Summit Park District
  • Village of Algonquin
  • Wauconda Township Pool Foundation
  • YMCA of Naperville
Accelerated Design

The Challenge: How do you design an outdoor water park that's open in time for NEXT year's swim season?
The Solution: SRBL planned a design schedule that shaved months off a typical time frame.

Read more