Elk Grove
Adminstration & Public Safety Facility
Cost of Construction: $21,200,000
Size: 106,000 SF
Status: Completed April 2009
Challenge/Goal: The center of the existing Village Hall/Police Station was demolished and the new Police Station constructed in its place. The Village wanted a building that was inviting to the public but kept officer safety a top priority.
Solution: The new complex includes a 25-yard shooting range, indoor underground parking, bullpen lock-up, Emergency Operations Center, and administration space. We kept “safety first” by creating a separate bond-out area adjacent to the sally port, but removed from the public entry. This facility is on track to receive LEED Gold Certification with over 13,000 SF of green roof, 21% of recycled materials, and plumbing fixtures that reduce water usage by 41%.