Harwood Heights
Village Hall and Police Department
Cost of Construction: $3,725,000
Size: 53,175 Total SF; 37,300 Renovated SF
Status: Completed Village Hall: October 2003, Police Station: June 2004
Challenge/Goal: The Village of Harwood Heights was operating out of an existing municipal building that was severely overcrowded. The Village purchased a manufacturing facility to convert into a municipal complex with very limited funding.
Solution: SRBL designed the municipal complex to be user friendly for both patrons and staff. The building contains a new Village Hall, Senior Center and Police Station. The Village Hall and Senior Center occupy 15,800 square feet, the police station occupies 21,500 square feet, and remaining space was reserved for future expansion.